2018-19 District Office construction

Click here for the summer construction postcard update, May 2018 (en español)

After community meetings, the Board of Trustees approved a plan in June 2016 to encompass construction of Stevenson, Theuerkauf, relocation of the Preschool program from the Slater site and rebuilding of the District Office. 

Construction of the new District Office building began in summer 2018. The District Office moved to the temporary multi-use housing behind its former location in August, and demolition of the current District Office took place in Fall 2018.

Construction on the new District Office continues, and is anticipated to be completed by August 2019. Construction was delayed slightly this spring in order to resolve unforeseen soil conditions. Underground utilities, building foundation and building fabrication are in progress.

The District Office has a new sign in the front. This sign, paid for with Measure G funds, will include accurate school and district names. Funding for construction and capital improvements, like school signs, come from restricted funds that can be used only for that purpose. The District used an innovative approach to piggyback on existing, competitive local government contracts to lower the sign cost and expedite installation.

The District has worked very hard over the years to do the work, funded by Measure G, to make facilities improvements and renovations at every school a reality. 

Construction timeline
Stev Preschool DO construction chart

Click here for the Fall 2017 construction update postcard, Sept. 2017 (en español)

Click here for the summer construction update postcard, May 12, 2017 (en español)


Phase 1 

Phase 2

Site plan for District office and stevenson