Huff Elementary construction

2020 Solar and Perimeter Fence projects

(Funded by Measure T)

Measure T, the $259 million bond issue passed in 2020, included plans for a variety of projects that will increase safety, efficiency and provide for short-term growth at our schools. 

HVAC
Replacement and improvements of HVAC equipment is scheduled.  HVAC filter replacements have been completed, and accordance with the CDC and County guidelines, will increase airflow and filtration reduce the chance of coronavirus spread. 

Security
Improving perimeter fencing and adding gates to completely enclose campus and fields in order to secure campuses and make COVID screening more efficient. Fencing and gates would be ornamental metal to match existing at campus frontage and 6’ high chain link fencing and gates at property lines and back of campus.  The construction timeline for this project is estimated to be October-January. 

The purpose of fencing is to control points of entry during school hours. It’s important to note that the public will have access to fields outside school hours. The intention is to secure campuses when students are present, and have gates open through a lock management system in the evenings and on weekends. 

Graham will get a new six-foot metal ornamental fencing around the library building, new gate at the office entrance, and six-foot ornamental metal fencing at the end of Classroom wings near the staff parking.

Click here for the perimeter fencing map (user friendly)
Click here for the Bubb/Huff Community Meeting Presentation

Solar
At the June 14, 2018 meeting the Board gave direction to continue with the concept of solar panels in MVWSD. In May 2020, the district got feedback on the design and placement of the solar arrays. The District is currently working with Engie and Sage on contract revisions and hopes to bring a contract to the board in October 2020.

Lighting
New light standards and/or bollard style light post to illuminate path of travel to/from campus and parking lots.

Public Restrooms
Huff will purchase and install prefabricated, standalone toilet buildings. The units would be maintained by the City and may be used afterhours by the public. This is an important security measure to ensure adults are not mixing with children in student restrooms.

Window Replacement
The District will replace existing, older single pane windows at Huff.

Additional Permanent Portable
One 960 SF standard classroom portable will be installed on a permanent concrete foundation. Location to be determined 

One 960 SF standard classroom portable will be installed on a permanent concrete foundation. Location to be determined 


 

2017-19 Classroom Modernization and a New Multi-Use Room

(18-month project funded by Measure G)

Summer 2019 
Accessible ramps were installed at classroom doors. District-owned portable classrooms were refreshed this summer,  meaning they will get new paint, carpet and whiteboards. Unused, leased portable classrooms will shuttered, and removal of these portables will happen in summer 2020.

The school got a new sign in the front. This sign, paid for with Measure G funds, will include accurate school and district names. Funding for construction and capital improvements, like school signs, come from restricted funds that can be used only for that purpose. The District used an innovative approach to piggyback on existing, competitive local government contracts to lower the sign cost and expedite installation.

January 2019
The conversion of the former multi-use room to library and special education rooms is complete. 

During Summer 2018
The classroom modernization, administration office reconfiguration, and expansion of one kindergarten classroom was completed by the end of summer 2018. The modernization and renovation of the existing multi-use room into the new library and two special education classrooms started in Summer 2018 and will be complete by winter 2018. 

Containers to house classroom furnishings and materials during the summer were delivered in mid May and placed in the side parking lots. Improvements to the school parking lot will happened over summer 2018, with the goal of making traffic flow safer and more efficient.

Over the 2017-18 school year
Construction work was concentrated behind the fence on the MUR, which is set to be completed in June. Work was finished on the creation of the MUR site pad, digging of the footings, installation of foundations, and hanging of steel. 


Huff construction chart


The District has worked very hard over the years to do the work, funded by Measure G, to make facilities improvements and renovations at every school a reality.

Click here for the summer construction postcard update, May 12, 2017 (en español)