Bubb Elementary construction

The 18-month project includes classroom modernization and a new multi-use room.

During Summer 2018
The classroom modernization, administration office reconfiguration, and expansion of one kindergarten classroom will be completed by the end of summer 2018. The modernization and renovation of the existing multi-use room into the new library and two special education classrooms will start in Summer 2018 and be complete by winter 2018. 

Containers to house classroom furnishings and materials during the summer will be delivered in mid May and placed in the side parking lot. During the summer, there will be no access to the front of the school, office and classrooms.

Over the 2017-18 school year
Construction work was concentrated behind the fence on the MUR, which is set to open in June. Work was finished on the creation of the MUR site pad, digging of the footings, installation of foundations, and hanging of steel. 

Work is planned for weekdays, from 7 a.m.- 7 p.m. Work on Saturdays may occur as construction deadlines near. There will be truck traffic coming and going on Barbara into the parking lot by YMCA for the removal of debris and delivery of new materials.

Dust may occur, and the District will follow procedures and best practices to reduce as much as possible any potential disruptions. The District will use the standard construction practice of watering down soil as it becomes dry to reduce dust. The equipment used on the site and dust control measures we employ comply with the Bay Area Air Quality Management District standards. Additionally, there is a green fabric screen applied to the fence to reduce the movement of dust across the site.


Bibb summer 2017 construction chart


As you know, the District has worked very hard over the years to do the work, funded by Measure G, to make facilities improvements and renovations at every school a reality. The results will be amazing. There will be new and updated classrooms, libraries and MURs. However, construction requires extra accommodations. We appreciate your support and understanding as we take one step closer to improving each of our schools for our students, staff and community.

Click here for the summer construction postcard update, May 12, 2017 (en español)

What each phase will look like (click to enlarge)

Phase 1 Phase 2 Phase 3

 

Bubb construction phase plan